NewsMilvian AI Strengthens North American Sales Leadership with Appointments of Todd Brinegar as Chief Revenue Officer and Patrick Pinkerton as Senior Vice President of Sales, North AmericaTodd Brinegar joins as CRO and Patrick Pinkerton as SVP of Sales, North AmericaRead more
Resources
Blog: Energy and grid risk

Winter peak demand in 2026 to 2027: what the grid outlook means for commercial buildings

Published November 23, 20265 min read
Milvian AI teamFacilities and infrastructure intelligence
Substation lit at night

NERC's 2026 to 2027 winter assessment finds no region at high risk of shortfall, but higher winter demand forecasts in 21 of 23 areas and elevated risk in prolonged cold. For a commercial building, the useful response is to know which loads set its morning winter peak, which of them can wait an hour, and who acts when the grid operator asks for conservation.

What NERC said on 18 November

The North American Electric Reliability Corporation published its 2026 to 2027 Winter Reliability Assessment on 18 November. It found no area at high risk of resource shortfall this winter. On-peak capacity grew 26.2 GW over the 2025 to 2026 winter, a 2.4 percent increase led by batteries and gas-fired generation, and fewer plants retired.

Demand is moving the other way. Winter peak demand forecasts rose in 21 of the 23 NERC assessment areas, driven mainly by data center expansion and electrification. New England is rated elevated because of limited gas pipeline capacity, SERC East can run short in the morning when solar output is low, and parts of MISO and SPP have local transmission limits that make imports hard in a wide cold event.

The risk sits in the long cold week, not the average

NERC's guidance draws on January 2026, when arctic events showed that operations planning has to allow for extreme conditions lasting 10 days or more. It also warns that short-term load forecasts tend to underestimate load in extreme cold, and asks state and provincial regulators to amplify public appeals to conserve electricity and gas.

A mild seasonal outlook does not remove that week. NERC staff noted that El Niño adds unpredictability and that ice storms and abnormal cold can sit inside a mild average. A building's exposure is decided on the morning the grid operator issues a conservation appeal and every rooftop unit on the block starts warming up at once.

What sets a commercial building's winter peak, and what to measure

LoadWhy it peaks in winterWhat to measure
Morning warm-up after night setbackEvery unit recovers the same setback at the same hour, often before occupants arrive.Demand by 15 minute interval from 5 a.m. to 9 a.m., per feeder or panel.
Electric reheat and duct heatersStrip heat runs hardest in the coldest hours and is often left enabled all season.Current on each reheat circuit, against outdoor air temperature.
Heat pump auxiliary heatBackup resistance heat engages as outdoor temperature falls and the heat pump loses capacity.Auxiliary heat run time and kW, split from compressor kW.
Heat trace and snow meltPipe and roof drain heating runs whenever it is cold, including empty weekends.Run hours, compared with the building schedule.
Domestic hot water and kitchensElectric water heaters recover after the morning draw, when heating is also at its peak.Water heater kW and the hour it peaks.
EV chargingFleet and staff chargers start when people arrive, on top of the warm-up load.Charger kW by hour, and how many sessions start before 9 a.m.

How Aqueduct finds the peak and trims it

aQ EnergySmart draws each site's electrical single line as a live energy balance: grid import, solar and backup generation on one side, HVAC, lighting, plug loads, services and losses on the other, with peak demand and 24 hour demand shown for every node. That turns a monthly kW figure on a bill into a list of the circuits that were on at the peak hour.

With the loads named, the fix is usually sequencing. Rooftop units can start their warm-up in staggered groups, reheat can lock out above a set outdoor temperature, and heat trace can follow the occupancy schedule. Where control is enabled, with owner approval, those rules run through relays or BACnet and Modbus field controllers, and the command history shows when each one acted.

Savings are set against a [weather-normalized baseline](/features/weather-normalized-baselining) built from heating degree days at the site, so a colder week is not mistaken for waste and a warmer one does not hide it.

Five things to settle before the first cold snap

  1. Find the hourPull last winter's interval data and mark the 15 minute window that set each month's peak. In most buildings it is the same window every week.
  2. Name the loads in that windowSub-meter the panels that feed warm-up, reheat and heat trace so the peak breaks into named systems.
  3. Stagger the warm-upSplit rooftop units or air handlers into groups that start 15 to 30 minutes apart, coldest zones first.
  4. Write the conservation playbookList the loads that can wait an hour during a grid appeal, the order to drop them, and the person who confirms it.
  5. Check what keeps reporting in an outageConfirm which meters and gateways have backup power, so the record of the event survives the event.

Where this is going

Demand growth from data centers and electrification is now showing up in winter as well as summer forecasts, and NERC added a new analysis of natural gas system risk to this year's assessment because constrained pipelines limit fuel for generators in cold snaps.

The weather adds its own uncertainty. NOAA's 12 November update gives a strong to very strong El Niño a better than 79 percent chance of lasting through January to March 2027. Buildings that know their morning peak by system can answer a conservation appeal in minutes; the rest will cut whatever is easiest to reach.

Sources

SourceLink
American Public Power Association, NERC 2026 to 2027 Winter Reliability Assessment (18 November 2026)publicpower.org
Utility Dive, El Niño a challenge for grid operators this winter: NERC (19 November 2026)utilitydive.com
NERC, 2026 to 2027 Winter Reliability Assessment (PDF)nerc.com
NOAA Climate Prediction Center, ENSO diagnostic discussion (12 November 2026)cpc.ncep.noaa.gov
Questions

Questions about this topic

Yes. Aqueduct breaks the main meter into sub-metered circuits and shows which ones were drawing power in the 15 minute window that set the peak. Morning warm-up, reheat and heat trace usually account for most of it in cold months. The method is covered under peak demand management.

Yes. Aqueduct keeps a ranked list of each site's deferrable loads with their typical kW, so the facilities team knows what to drop first and by how much. The meter then shows whether the drop happened and how long it held. See how teams manage peak demand and tariffs.

Aqueduct uses heating degree days so a cold week is judged against what that weather should cost, not against last month. The regression on usage and degree days sets expected use per site, and only the gap counts as waste or savings. More on the weather-normalized baseline.

Yes. Each rooftop unit's digital twin records when heating stages and fans start, so Aqueduct can show how many units began warming up in the same quarter hour. Staggering those starts is often the cheapest winter peak reduction available. Read more on HVAC energy optimization.

See Aqueduct on your own facility.

Bring a site, a utility bill or a question. We will show you where the loss is.